Replace a Resource Across all Tasks in a Plan
-
Click the ellipsis in the Work Plan toolbar, then select Resources > Replace Resources > All Tasks. The Resource Replace form will open.
-
Complete the Resource Replace form.
-
Select a resource to replace from the Resource to Replace drop down.
-
Select a replacement resource:
-
Click Replace.
Replace a Resource for Selected Tasks
-
Select the desired work items from the Plan Grid. You can select multiple work items by holding down the CTRL key.
-
Click the ellipsis in the Work Plan toolbar, then select Resources > Replace Resources > Selected Task(s). The Resource Replace form will open.
-
Complete the Resource Replace form.
-
Select a resource to replace from the Resource to Replace drop down.
-
Select a replacement resource:
-
Click Replace.